NEW QUESTION 36
An installer is using 1/2 in lag boits to secure roof-monitoring hardware to rafters through a roof deck. Which of the following should the installer predrill?

  • A. A pilot hole one-half the length of the bolt
  • B. A 5/16 in pilot hole through the roof into the rafter
  • C. A 1/8 in, pilot hole through the roof into the rafter
  • D. A pilot hole one-fourth the length of the bolt

Answer: B

 

NEW QUESTION 37
Which of the following should a PV installer do during dc insulation resistance testing?

  • A. Close ac and dc disconnects and have the system running for at least 5 minutes before testing.
  • B. Remove surge suppression equipment from the circuit being tested.
  • C. Wait until is raining and all wiring is damp to conduct the test.
  • D. Connect the megohmmeters's negative terminal to the dc circuit insulation

Answer: D

 

NEW QUESTION 38
Which of the following is an NEC requirement regarding access for large-scale PV electric power production facilities?

  • A. All fencing and associated gates must have ac and dc current and voltage exposure labvels and must be electrically isolated from the solar facility.
  • B. Access to remote isolating equipment for servicing is allowed for individual other than qualified persons when the equipment is enclosed within a secure structure.
  • C. Arc flash warning labels must be field-applied by the installer at all access points for qualified persons and at the point of the utility interconnection directory.
  • D. Field-applied hazard markings must be installed, and access to the supply station is to be restricted by fencing or other adequate means.

Answer: D

 

NEW QUESTION 39
Which of the following voltages should be included on the dc disconnected label to indicate MAXIMUM system voltage?

  • A. Source circuit V
  • B. Non-temperature-corrected V
  • C. Temperature-corrected V
  • D. 600 V

Answer: C

 

NEW QUESTION 40
When performing a system checkout after completing the installation, what is the SAFEST sequence of tasks to detect installation errors before closing any disconnects to the inverter, charge controller, or batteries?

  • A. Perform visual inspection, install source circuit fuses, and measure open-circuit voltage.
  • B. Install source circuit fuses, verify that all equipment-grounding conductors are secure, and measure ac line voltage.
  • C. Perform visual inspection, install source circuit fuses, and measure open-circuit current.
  • D. Perform visual inspection, check polarity and measure open-circuit voltage.

Answer: D

 

NEW QUESTION 41
A PV system is located at 41 N latitude. The sun angle is 23 on December 21 at solar noon. Assuming that the
65 ft tree is directly south of the PV array and will grow 20 ft. over the life of the PV system, what is the MNIMUM distance the tree to the button of the prevent shading?

  • A. 98 ft.
  • B. 153 ft.
  • C. 201 ft.
  • D. 167 ft.

Answer: C

 

NEW QUESTION 42
A PV system installation utilizes micro inverters connected to each module of the array. Each micro inverter has a nominal rated output of 250WV. Single phase. The microinverters are listed so that multiple inverters may be connected in parallel to a single feeder circuit, and each inverter has ancable and connector rated for
30A. What is the MAXIMUM number of inverters that may be wired together on a single 30A feeder circuit?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 43
A metal condult containing an array circuit with Vmo of 400Vdc is connected to a metal enclosure at the location where the concentric knockouts have been punched by the manufacturer. Which method of attachment should be used?

  • A. Grounding bushing
  • B. Insulated bushing
  • C. Threaded coupling
  • D. Sealing locknut

Answer: A

 

NEW QUESTION 44
An installer has decided to use 31 in. long. 3.1/2 in diameter conical ground screws as the footings for a
3.840W solar electric system. Access to he is too difficult to pour concrete footings. The soll is classified as sandy loam. The design wind speed is 90 mph with an uplift force of 32 ibs/ft2. What is the MINIMUM number of screw required to resist uplift loads?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 45
On a PV system larger than 100kw, which PV array design will provide the HIGHEST degree of performance monitoring.
Granularity, and ease of troubleshooting performance issues?

  • A. Multiple-string inverter system with data acquisition system located at each inverter.
  • B. Multiple-string inverter system with monitored dc-to-dc converters located at each module
  • C. Central inverter with data acquisition system located at the inverter.
  • D. Multiple-string inverter system with data acquisition system located at each dc combiner

Answer: D

 

NEW QUESTION 46
A dwelling has a 200A main load center with a 150 main breaker. Which of the following is the MOST powerful 240V inverter that can be installed in the house using the existing main panelboard with a backfed breaker?

  • A. 21, 600W
  • B. 7, 689W
  • C. 17, 280W
  • D. 9, 600W

Answer: C

 

NEW QUESTION 47
An installer was asked to provide a means to measure the voltage of each battery in a system. The bank is located 50 ft.
From the data logger. The installer will be using shielded. Twisted pairs of instrumentation wiring, all run in the bundle a conduct.
The signals are connected to isolated and ungrounded inputs at a data logger. Which safely precaution is MOST needed to protect the instrumentation wiring?

  • A. The instrument wiring must be large (larger than # 18 AWG) to handle current from each battery and must be a double- insulated type.
  • B. An appropriately rated and sized of resistive elements for each twisted pair be located at, or very near to, the data logger terminals
  • C. Individual nonfused disconnects are required for each set of wiringbecause all of the signals must be isolated from each other.
  • D. Each set of twisted pairs must be provided with properly rated fuses that are physically located at the battery.

Answer: D

 

NEW QUESTION 48
A grid-interactive PV system with battery backup is being installed with a ground-mounted PV array located
200 ft, from the inverter and batteries. The dc PV output circuit has overcuit has overcurrent protection rated from 30A. To reduce voltage drop between the array and batteries, the output circuit wire size was determined to be 6 AWG. The fused dc disconnect between the inverted and batteries is rated for 300A. What is the required size of the equipment grounding conductor between the metal battery case and the inverter?

  • A. 10 AWG
  • B. 6 AWG
  • C. 4 AWG
  • D. 8 AWG

Answer: C

 

NEW QUESTION 49
A commercial 600v carport-mounted PV system is installed with rigid running under the parking lot to an inverter pad located at the edge of the parking lot. At what depth below the parkinglot base MUST condult be buried?

  • A. 18 in.
  • B. 36 in.
  • C. 12 in.
  • D. 24 in.

Answer: D

 

NEW QUESTION 50
A PV system equipped with rapid shutdown requires a label stating ''RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM''.
Which is the BEST description of where this label is required?

  • A. On or within 3 ft. of the ac disconnect
  • B. On or within 3 ft. of the ac disconnect
  • C. On or within 3 ft. of the ac disconnect
  • D. On or within 3 ft. of the ac disconnect

Answer: D

 

NEW QUESTION 51
An 8 AWG bare copper equipment ground conductor (EGC) is wire tied to the module mounting structure of a commercial rooftop solararray. After a few years of operation, some spots on the EGC begin to turn a green color and appear to be corroding more significantly that other places. What would the MOST likely cause of the problem?

  • A. Nyton wire ties in contact with the copper wire
  • B. Bypass dlode failures inducing current on the EGC
  • C. Array racking touching the EGC at multiple points
  • D. A break in the EGC, leaving the array ungrounded

Answer: C

 

NEW QUESTION 52
An 8KWsc roof-mounted array is placed on a school building. The inverter is located within 1 ft, of the array boundary and has an integrated ac-and dc-disconnecting switch. The system is to be connected to a 400A load center, protected by a 400A main breaker. Which of the following MUST be included to meet NEC requirements?

  • A. An ac-disconnect label with the location of the rooftop dc-disconnect switch.
  • B. A readily accessible dc disconnect with rapid shutdown initiation device permanently labeled
  • C. A readily accessible ac-disconnecting switch, who location is identified on the system directory
  • D. A rapid shutdown initiationdevice operating contractor within 1 ft, of the array to de-energize the dc subarrays

Answer: C

 

NEW QUESTION 53
How should stratification be eliminated in a set of large, stationary, stationary flooded lead-acid batteries?

  • A. Enable equalization.
  • B. Rotate the battery positions
  • C. Discharge to 80 depth of discharge.
  • D. Add 50% diluted sulfuric acid.

Answer: A

 

NEW QUESTION 54
A PV technician is installing a 6.5KWac inverter using a 40A backfed breaker. The single line shows a 200A panelboard with a 200A breaker, but the installer finds that the panelbord actually has a 150A main breaker.
Which of the following is the CORRECT installation option?

  • A. Complete the installation as noted above.
  • B. Replace the 200A panel with a 150A panel.
  • C. Install a 30A backfed circuit breaker.
  • D. Change the main circuit breaker to a 200A unit.

Answer: A

 

NEW QUESTION 55
Which electrical connection requires the use of a torque device to complete the connection per NEC requirements?

  • A. Screw terminals on an ac receptacle outlet
  • B. Underground direct-burial twist-on wire connector
  • C. Crimp-on log to the battery cable
  • D. Soldered splices in a conduit body

Answer: C

 

NEW QUESTION 56
......