SAP New 2021 C-TS4CO-2020 Test Tutorial (Updated 182 Questions) [Q72-Q95]

Share

SAP New 2021 C-TS4CO-2020 Test Tutorial (Updated 182 Questions)

C-TS4CO-2020 Exam Questions Dumps, Selling SAP Products


SAP S/4HANA Management Accounting Certification Exam Topics:

Topic AreasTopic Details, Courses, BooksWeighting
Organizational Assignments and Process IntegrationDefine scopes and processes in Management Accounting, cross-company code design, sub-contracting, production execution, sales pricing, inbound freight, stock transfers, inventory valuation and transfer pricing, work in process rules and high-level requirements for organization units. Configure budgeting and availability control settings and period end closing, define statistical key figures and assign the controlling area to company codes and operating concern. Check number ranges and first integration flows with other modules (CO), and configure versions.

TS4F03, TS4F04 OR S4F22, S4F23, S4F25, S4F28, S4F29

8% - 12%
Cost Center AccountingDefine, create and configure cost centers, cost center hierarchies and cost center groups. Determine usage of Cost Center Accounting and type of planning functionality, cost center accounting activity types, cost center characteristics and attributes, planning requirements, plan allocations requirements and actual allocations for cost centers. Configure period end closing for CCA.

TS4F03 OR S4F22

> 12%
Internal OrdersDistinguish between order category and order type. Determine plan data, commitments and actual requirements for internal orders and determine period-end closing activities. Define, create and configure internal orders and create a concept for internal order accounting, and customize internal order accounting, determine settlement rules and configure period-end closing for IOA.

TS4F03 OR S4F22

8% - 12%
ReportingDetermine general reporting requirements for cost centers, configure cost center reporting, and create report painter reports and drill-down reports.

TS4F03, TS4F04 OR S4F22, S4F25, S4F29

8% - 12%
Profitability AnalysisDefine value fields, characteristics and summary characteristics, determine planning, actual and process flow and security requirements, design process flows and develop authorization concept for reporting of FI / CO data. Configure profitability analysis and determine the operating concern, and assignment to controlling area. Define currency and assign the chart of accounts, result analysis and revenue recognition (in cooperation with FI and SD), and configure period-end closing for PA.

TS4F04 OR S4F29

> 12%
Product Cost PlanningDetermine and configure product cost planning, define interface from CO-PCP (Product Cost Planning) to CO-PA (Profitability Analysis) and costing versions for alternative costings, determine cost elements structure, cost component structure, planning requirements, costing variants and multi-level costings, and carry out a Price update in the material master record.

TS4F03 OR S4F23

> 12%
Cost Object ControllingDetermine and configure cost object controlling - planning and actuals, and customize and complete cost object controlling in a make to stock scenario and in a make to order scenario. Define WIP, results analysis, variances and revenue recognition (in cooperation with FI and SD) and configure period end closing for cost objects.

TS4F03, TS4F04 OR S4F25

> 12%
Profit Center AccountingCreate organizational charts for profit centers, determine Profit Centers (in FI in the new GL), create Profit Centers and check master data assignments, and configure period-end closing for PCA.

TS4F04 OR S4F28

< 8%


SAP S/4HANA Management Accounting Certification Exam Details:

Schedule ExamSAP Training
Number of Questions80
Passing ScoreC_TS4CO_2020 - 64%
C_TS4CO_1900 - 63%
Reference BooksTS4F03 (SAP S/4HANA 2020)
TS4F04 (SAP S/4HANA 2020)
TS4F03 (SAP S/4HANA 1909)
TS4F04 (SAP S/4HANA 1909)
Exam CodeC_TS4CO_2020
LevelAssociate
Exam NameSAP Certified Application Associate - SAP S/4HANA for Management Accounting (SAP S/4HANA 2020)
SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates (SAP S/4HANA 1909)
Sample QuestionsSAP S/4HANA Management Accounting Certification Sample Questions
Exam Price$550 (USD)
Duration180 mins

 

NEW QUESTION 72
Which key performance indicators (KPIs) does profit center accounting help you report? There are TWO correct answers for this question

  • A. Profit contribution of a department
  • B. Contribution of new customers to gross revenue
  • C. Impact on sales of a marketing activity
  • D. Return on capital expenditure investment

Answer: A,D

 

NEW QUESTION 73
What are some of the characteristics of SAP Core Data Service (CDS) views? 3 answers

  • A. CDS views are considered system modifications
  • B. CDS views have ready-to-use content
  • C. CDS views support authorizations
  • D. CDS views have no latency
  • E. CDS views duplicate data for reporting efficiencies

Answer: A,C,D

 

NEW QUESTION 74
Which object do you have to assign the cost component structure to?

  • A. Material master record
  • B. Costing type
  • C. Valuation variant
  • D. Costing variant

Answer: D

 

NEW QUESTION 75
What can you analyse in detail when you transfer the cost component split from product cost planning to costing-based CO-PA?

  • A. Cost of good sold
  • B. Variance categories
  • C. Cost of goods manufactured
  • D. Sales revenues

Answer: A

 

NEW QUESTION 76
Which of the following are typical activities of the sales planning phase in SAP S/4HANA? There are TWO correct answers for this question

  • A. Transfer of GL account data
  • B. Top-down distribution
  • C. Manual entry of data
  • D. Bottom-up distribution

Answer: A,C

 

NEW QUESTION 77
You enter the actual activity quality for work and vacation in the cross-application time sheet. Which options can you choose in the master data of the activity type to ensure the quantities and values are posted in Management Accounting? There are TWO correct answers for this question

  • A. Manual entry, manual allocation
  • B. Manual entry, indirect allocation
  • C. Manual entry, no allocation
  • D. Indirect determination, indirect allocation

Answer: B,C

 

NEW QUESTION 78
Which objects can you plan in cost center accounting? There are THREE correct answers for this question

  • A. Non-operating expense accounts
  • B. Statistical key figures
  • C. Balance sheet accounts
  • D. Secondary cost accounts
  • E. Activity prices

Answer: A,B,D

 

NEW QUESTION 79
Which of the following objects can be selected in templates for activity-based costing? 2 answers

  • A. Cost center/activity typ
  • B. Business process
  • C. WBS element
  • D. internal order

Answer: A,B

 

NEW QUESTION 80
You want to define requirement levels for users for the authorization check in Profitability Analysis reporting. Which requirement level would you set to enable user access to all the interactive drill down functions?

  • A. 0 - ALL
  • B. 1 - Level 1
  • C. 2 - Level 2
  • D. 3 - ALL

Answer: A

 

NEW QUESTION 81
Where do you activate commitment management for internal orders? There are TWO correct answers for this question

  • A. In the controlling area
  • B. In the company code
  • C. In the budget profile
  • D. In the order type

Answer: A,D

 

NEW QUESTION 82
You post a billing document in Sales and Distribution (SD). What data flows to profit center accounting?
3 answers

  • A. Payment discount
  • B. Accruals
  • C. Order quantity
  • D. Sales deductions
  • E. Revenues

Answer: A,B,D

 

NEW QUESTION 83
Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question

  • A. Create a cost center without specifying a standard hierarchy
  • B. Assign a standard hierarchy to several controlling areas.
  • C. Append nodes and cost centers to a node of the standard hierarchy.
  • D. Reassign a cost center to another node of the standard hierarchy.

Answer: C,D

 

NEW QUESTION 84
How do you define the relationship between an operating concern and a controlling area ?

  • A. Many-to-one (N:l)
  • B. One-to-one (1:1)
  • C. One-to-many (1:N)
  • D. Many-to-many(N:N)

Answer: C

 

NEW QUESTION 85
On which organizational level do you maintain profit center accounting in SAP S/4HANA?

  • A. Controlling area
  • B. Operating concern
  • C. Company code
  • D. Financial statement version

Answer: A

 

NEW QUESTION 86
In your company, you tend to go through many reorganizations leading to extra master data maintenance work. Which grouping functionality can save you time maintaining profit center groups?

  • A. Defining flexible hierarchies
  • B. Configuring derivation rules
  • C. Copying groups with suffix
  • D. Creating multi-dimension sets

Answer: C

 

NEW QUESTION 87
What tasks are performed by the system during activity allocation? There are TWO correct answers for this question

  • A. A primary costs G/L account is used for debiting and crediting
  • B. The cost element is derived from the master data for the activity type
  • C. The allocation amount is calculated based on the quantity and price of the activity
  • D. The sender cost object is debited and the receiver cost object is credited

Answer: B,C

 

NEW QUESTION 88
What master data objects can you set up using time-based fields?

  • A. Standard hierarchies
  • B. Cost centers
  • C. Activity types
  • D. Statistical key figures

Answer: B,D

 

NEW QUESTION 89
You configured an overhead costing sheet that uses the quantity-based overhead approach to calculate the overhead amount. What is required for the amount to be calculated?

  • A. Settlement rules with valid receiver objects
  • B. Statistically figures with values for the period
  • C. Activity types with actual or plan quantities maintained
  • D. Cost accounts with the option to record quantity

Answer: C

 

NEW QUESTION 90
Which criteria do you use to specify the G/L account for the work in process (WIP) settlement? There are THREE correct answers for this question

  • A. Results analysis method
  • B. Results analysis cost element
  • C. Results analysis category
  • D. Results analysis profit center
  • E. Results analysis version

Answer: A,C,E

 

NEW QUESTION 91
How does SAP S4/HANA determine if a characteristic value is valid in Profitability Analysis?

  • A. By defining the characteristic value as a value field
  • B. By defining the characteristic value in the check table
  • C. By defining the characteristic value in the field catalog
  • D. By defining the characteristic value as a key figure

Answer: B

 

NEW QUESTION 92
You want to creat cost centers for you company. What is the prerequisite to building an organizational structure for overhead cost controlling?

  • A. Cost center category
  • B. Standard hierarchy top node
  • C. Cost center type
  • D. Functional area

Answer: B

 

NEW QUESTION 93
When you create a planning layout, whih objects can you use to define the data columns ? 3 Answers

  • A. Summarization level
  • B. Distribution key
  • C. Formulas
  • D. Value fields
  • E. Characteristics

Answer: C,D,E

 

NEW QUESTION 94
Which receiver must be allowed in the settlement profil of a product cost collector?

  • A. Business process
  • B. Order
  • C. Material
  • D. Cost center

Answer: C

 

NEW QUESTION 95
......

C-TS4CO-2020 Cert Guide PDF 100% Cover Real Exam Questions: https://www.testvalid.com/C-TS4CO-2020-exam-collection.html